In December 2020, Regina Mundi and Dante Alighieri school communities were provided with an update regarding our redevelopment.
As shared in the communication, Regina Mundi students will remain on site at their current school for one year while construction to retrofit the Dante Alighieri building is complete.
Following construction completion in 2022, Regina Mundi will move into the renovated school at 60 Playfair Avenue. This redevelopment plan will eliminate expressed health and safety concerns, as the Dante construction site will be separated with no public access until completion.
Community Updates and Resources
Here are the latest updates and information regarding the new construction at Regina Mundi Catholic School.
December 2023
June 2023
February 2022
February 2021
December 2020
June 2020
April 2020
March 2020
February 2020
Status Updates
December 2019:
The first Local Design Committee (LDC) meeting was held on October 15, 2019. The Regina Mundi renovation design is progressing independently of plans for the new Dante Alighieri project. The architect is reviewing LDC feedback and will present design revisions at the January LDC meeting.
Project Information
Project Type: Elementary Retrofit
Anticipated Occupancy: January 8, 2024
Service Quality Supervisor: S. Talarico (#3)
Project Supervisor: L. Silva
Architect: CS&P Architects
Contractor: Corebuild Construction Ltd.